Budget Variance report
The Budget Variance Report shows the budget, the actual amount, and the difference for each period, for every submitted budget. Use it to see whether spending is ahead of or behind plan.
For example, a marketing budget of 120,000 is spread at 10,000 a month. By the end of March, actual spending is 27,500.
Filters
| Filter | Use |
|---|---|
| Company | The company of the budgets |
| From Fiscal Year, To Fiscal Year | The years to show |
| Period | Monthly, Quarterly, Half-Yearly, or Yearly columns |
| Budget Against | Cost Center, Project, or an accounting dimension |
| Dimension Filter | One or more values of the selected Budget Against |
| Show Cumulative Amount | Shows running totals up to each period, useful for seasonal spending |
Columns
| Column | Meaning |
|---|---|
| Budget | The budget for the period |
| Actual | Submitted entries on the same account and cost center, project, or dimension |
| Variance | Budget minus actual. ERPNext colors negative values, where actual exceeds budget, differently from positive values. |
Troubleshooting
The report is empty
The report lists only accounts with a submitted budget. Check that a budget exists for the company, years, and Budget Against.
The actual amount is lower than expected
Some documents use another cost center, project, account, date, or dimension. Compare with the General Ledger using the same filters.