Create a Work Order
A Work Order tells the shop floor to make a quantity of one item. It lists the raw materials to use, the operations to perform, and the warehouses to use. After you submit it, you transfer the raw materials, record the operations, and record the finished goods.

Prerequisites
- A submitted BOM for the item.
- For a BOM with operations: the operations and workstations.
You can also create Work Orders from a Production Plan or from a Sales Order.
Create a Work Order
- Open the Work Order list and select New.
- In Item To Manufacture, select the item. ERPNext fills in its default BOM No. You can select another BOM.
- Enter the Qty To Manufacture. ERPNext fills in the Required Items table from the BOM.
- Select the warehouses:
- Work-in-Progress Warehouse: where materials go during production. You can select a group warehouse.
- Target Warehouse: where the finished goods go.
- Scrap Warehouse: where scrap and other secondary items go.
- Default source Warehouse, or the Source Warehouse of each row in Required Items: where the raw materials are stored. You can select a group warehouse.
- In Scheduling & Costing, set the Planned Start Date. It defaults to now.
- Review the Operations table, if the BOM has operations. You can change the workstation and the time of each operation.
- Submit the Work Order.
You can save a Work Order without warehouses, but you must set them before you submit.
TIP
Set default warehouses on the Company, in the Manufacturing section. New Work Orders take them automatically.
When you submit a Work Order with operations, ERPNext creates a Job Card for each operation and schedules it. Learn about capacity planning.
Production options
| Option | What it does |
|---|---|
| Use Multi-Level BOM | Selected by default. Plans the raw materials of the sub-assemblies. Clear it if you make the sub-assemblies in separate Work Orders. See Manage multi-level BOMs. |
| Skip Material Transfer to WIP Warehouse | Skips the transfer of raw materials to the Work-in-Progress Warehouse. The Manufacture Stock Entry consumes the raw materials directly from the source warehouses. Use it when one person handles both stores and production, or when you transfer materials in bulk. |
| Backflush Raw Materials From Work-in-Progress Warehouse | Shown when you skip the transfer. Consumes the raw materials from the Work-in-Progress Warehouse instead of the source warehouses. |
| Transfer Material Against | Work Order: transfer all materials at once. Job Card: transfer materials for each operation. ERPNext takes the default from the BOM. |
| Allow Alternative Item | Lets you replace a raw material with an alternative item. Learn about Item Alternative. |
| Reserve Stock | Reserves the raw materials for this Work Order. See Reserve stock for production. |
| Sales Order | Links the Work Order to a Sales Order. |
| Project | Links the Work Order to a Project, for example in engineer-to-order production. |
The Required Items table
Each row shows one raw material and its quantities:
| Column | Meaning |
|---|---|
| Required Qty | The quantity from the BOM for the quantity to manufacture. |
| Transferred Qty | The quantity moved to the Work-in-Progress Warehouse. Not updated when you skip the transfer. |
| Consumed Qty | The quantity used in production. |
| Returned Qty | The quantity returned from the Work-in-Progress Warehouse. |
| Available Qty at Source Warehouse | The stock in the source warehouse. |
| Available Qty at WIP Warehouse | The stock in the Work-in-Progress Warehouse. |
You can change the raw materials and quantities only when Allow Editing of Items and Quantities in Work Order is selected in Manufacturing Settings.
The Operations table and operating cost
Each row of the Operations table shows the operation, the workstation, the planned time, and the Status: Pending, Work in Progress, or Completed. Job Cards update the status, the Completed Qty, and the actual times.
The Operation Cost section shows:
- Planned Operating Cost: from the BOM operations.
- Actual Operating Cost: from the Job Cards.
- Additional Operating Cost: other costs that you enter.
- Total Operating Cost: actual cost plus additional cost.
Work Order statuses
| Status | Meaning |
|---|---|
| Draft | Not submitted. |
| Not Started | Submitted, no materials transferred yet. |
| In Process | Production started. |
| Completed | All the quantity is made. |
| Stopped | Stopped by a user. It can be re-opened. |
| Closed | Closed by a user. It cannot be re-opened. |
| Cancelled | Cancelled. |