Schedule operations with capacity planning
Capacity planning schedules each operation of a Work Order on a workstation. It tells you when each job runs and helps you decide whether you can accept a new order. Capacity planning is on by default.
Prerequisites
- Workstations with Working Hours, a Holiday List, and a Job Capacity.
- A BOM with With Operations selected, and an Operation Time for each operation.
How ERPNext schedules operations
When you submit a Work Order with operations:
- ERPNext starts from the Planned Start Date of the Work Order.
- For each operation, it looks for the first free slot on the workstation, in order. A slot is free when it is inside the working hours, not on a holiday, and the workstation runs fewer jobs than its Job Capacity.
- It keeps the Time Between Operations (Mins) gap between operations.
- It creates a Job Card for each operation with the scheduled times in Scheduled Time Logs. The Job Card shows Expected Start Date and Expected End Date.
ERPNext looks for a slot in the next Capacity Planning For (Days) days, 30 by default. If it finds none, it stops the submission.

Configure capacity planning
In Manufacturing Settings, in the Job Card and Capacity Planning tab:
| Setting | Use it to |
|---|---|
| Capacity Planning For (Days) | Set how far ahead ERPNext looks for free slots. |
| Allow Overtime | Schedule operations outside working hours. |
| Allow Production on Holidays | Schedule operations on holidays. |
| Time Between Operations (Mins) | Keep a gap between operations. |
| Disable Capacity Planning | Turn off scheduling completely. |
Set the job capacity of a workstation
Job Capacity on the workstation is the number of jobs that can run at the same time. For example, if a workstation can run 10 jobs at once, enter 10.

View the schedule on a calendar
Open the Work Order list and switch to the Calendar view. Each Work Order shows from its planned start date to its planned end date.