Plan raw materials for production ​

A Production Plan calculates the raw materials for its finished goods and sub-assemblies. It then creates Material Requests to buy them or to transfer them from other warehouses.

Prerequisites ​

  • A draft Production Plan with its Assembly Items and, if needed, Sub Assembly Items.

Get the raw materials ​

  1. In the For Raw Materials section, select the For Warehouse. This is where the raw materials are needed. Stock Entries for production look for raw materials in this warehouse.
  2. Select the options that you need (see below).
  3. Select one button:
    • Get Items for Purchase Only: fills in the Raw Materials table with the quantities to buy.
    • Get Items for Purchase / Transfer: asks for the warehouses to transfer from. ERPNext suggests a transfer for the stock in those warehouses, and a purchase for the rest. If you select a group warehouse, ERPNext checks its child warehouses.
  4. Review the Raw Materials table. The Type of each row is the purpose of its Material Request, for example Purchase or Material Transfer.

After you submit the plan, select Create > Material Request.

Options for raw materials ​

OptionWhat it does
Include Non Stock ItemsIncludes items that have Maintain Stock cleared.
Include Subcontracted ItemsAdds the raw materials of subcontracted items when Include Exploded Items is cleared.
Consider Minimum Order QtyRaises each quantity to the minimum order quantity of the item.
Include Safety Stock in Required Qty CalculationAdds the safety stock of the item to the required quantity.
Consider Projected Qty in Calculation (RM)Orders only the shortfall: Required Qty = Reqd Qty (BOM) − Projected Qty.
Raw Material Group WarehouseA group warehouse whose child warehouses ERPNext checks for stock. Materials still arrive in For Warehouse.

Example: order only the shortfall ​

To finish production you need 100 units of item A. You have 50 in stock and 20 on an open Purchase Order.

  • With Consider Projected Qty in Calculation (RM) selected, the required quantity is 100 − (50 + 20) = 30.
  • With it cleared, the required quantity is 100.

Download the material plan ​

  1. Select Download Required Materials.
  2. Select the warehouses in which to check the available stock.

ERPNext downloads a spreadsheet with the raw materials, the required quantities, and the stock in each selected warehouse.

Spreadsheet with the raw materials of a Production Plan