About production and material planning
Production planning answers three questions: what to make, what materials to get, and when the shop floor can do the work. ERPNext answers them with a set of tools that build on each other.
Planning tools
| Tool | Question it answers |
|---|---|
| Production Plan | Which finished goods and sub-assemblies do I make for these Sales Orders or Material Requests? |
| Raw material planning | Which raw materials do I buy or transfer for this plan? |
| Material Requirements Planning (MRP) | What do I need, and when, for my forecast and long-term demand? |
| Capacity planning | When can each workstation do the work? |
| Production Plan scheduling (version 17) | When will each item of the plan be finished, given machine capacity? |
| Plan Visualizer (version 17) | Is the plan on track, and what is holding it up? |
| Stock reservation | How do I keep materials for one plan or Work Order from being used elsewhere? |
How the tools fit together
- Demand comes from Sales Orders, Material Requests, and sales forecasts.
- A Production Plan, or a Master Production Schedule for MRP, collects the demand for finished goods.
- ERPNext explodes the BOMs to find the sub-assemblies and raw materials.
- The plan creates Work Orders for items that you make, subcontracting Purchase Orders for items that a supplier makes, and Material Requests for items that you buy.
- When you submit a Work Order, capacity planning schedules each operation on a workstation.
Short-term and long-term planning
A Production Plan works from confirmed demand: open Sales Orders and Material Requests. It suits make-to-order production and short horizons.
MRP adds sales forecasts and Sales Order delivery schedules. It uses item lead times to calculate when to release orders. It suits make-to-stock production and longer horizons.