About production and material planning ​

Production planning answers three questions: what to make, what materials to get, and when the shop floor can do the work. ERPNext answers them with a set of tools that build on each other.

Planning tools ​

ToolQuestion it answers
Production PlanWhich finished goods and sub-assemblies do I make for these Sales Orders or Material Requests?
Raw material planningWhich raw materials do I buy or transfer for this plan?
Material Requirements Planning (MRP)What do I need, and when, for my forecast and long-term demand?
Capacity planningWhen can each workstation do the work?
Production Plan scheduling (version 17)When will each item of the plan be finished, given machine capacity?
Plan Visualizer (version 17)Is the plan on track, and what is holding it up?
Stock reservationHow do I keep materials for one plan or Work Order from being used elsewhere?

How the tools fit together ​

  1. Demand comes from Sales Orders, Material Requests, and sales forecasts.
  2. A Production Plan, or a Master Production Schedule for MRP, collects the demand for finished goods.
  3. ERPNext explodes the BOMs to find the sub-assemblies and raw materials.
  4. The plan creates Work Orders for items that you make, subcontracting Purchase Orders for items that a supplier makes, and Material Requests for items that you buy.
  5. When you submit a Work Order, capacity planning schedules each operation on a workstation.

Short-term and long-term planning ​

A Production Plan works from confirmed demand: open Sales Orders and Material Requests. It suits make-to-order production and short horizons.

MRP adds sales forecasts and Sales Order delivery schedules. It uses item lead times to calculate when to release orders. It suits make-to-stock production and longer horizons.