Create a project
A Project is a planned piece of work that you divide into tasks, for example launching a new product, installing equipment for a customer, or opening a new office. The project collects the progress of its tasks and the cost and revenue of everything linked to it.
Prerequisites
- For a customer project, the Customer exists, and optionally the Sales Order.
- To start from a plan, a project template exists.
Create a project
- Open the Project list and select Add Project.
- Enter the Project Name.
- Optionally, select a template in From Template. ERPNext creates its tasks when you save.
- Set the Expected Start Date and the Expected End Date.
- Optionally, select the Project Type, the Priority (Low, Medium, or High), and the Department.
- Select the % Complete Method. See Choose how progress is measured.
- Save the project.
You can also create a project from a submitted Sales Order with Create > Project.
The Status starts as Open. You can set it to On hold, Completed, or Cancelled. Is Active marks whether the project is still active.
Choose how progress is measured
% Complete Method decides how ERPNext calculates % Completed:
| Method | Calculation |
|---|---|
| Manual | You enter % Completed yourself. |
| Task Completion | Completed and cancelled tasks ÷ all tasks. This is the default. |
| Task Progress | Sum of the % Progress of all tasks ÷ number of tasks. |
| Task Weight | Sum of each task's % Progress × its Weight ÷ the total weight of all tasks. |
For example, a project has three tasks:
| Task | % Progress | Weight | Status |
|---|---|---|---|
| Build | 100 | 0.4 | Completed |
| Operate | 100 | 0.2 | Completed |
| Transfer | 50 | 0.2 | Open |
- Task Completion: 2 ÷ 3 = 66.67%.
- Task Progress: (100 + 100 + 50) ÷ 3 = 83.33%.
- Task Weight: (100 × 0.4 + 100 × 0.2 + 50 × 0.2) ÷ 0.8 = 87.5%.
When % Completed reaches 100, ERPNext sets the status to Completed, unless you set the project to On hold or Cancelled.
Link the project to a customer
In the Customer Details section, select the Customer and the Sales Order. The project then shows the sales amount of the order, and you can follow the work against the agreed scope.
Give users access
In the Users table, add website users who can see the project in the portal, such as customers, freelancers, or contractors. For each user, you can:
- Send a welcome email.
- Allow them to view attachments with View attachments.
- Hide the timesheets with Hide timesheets.
See Share a project with customers.
Use Notes for any other information about the project.
Follow the project
The project fills these fields from linked documents:
| Field | Comes from |
|---|---|
| Actual Start Date (via Timesheet) | The first timesheet row for the project. |
| Actual End Date (via Timesheet) | The last timesheet row for the project. |
| Actual Time in Hours (via Timesheet) | All timesheet rows for the project. |
| Total Costing Amount (via Timesheet) | The costing amounts of the timesheets. |
| Total Billable Amount (via Timesheet) | The billable amounts of the timesheets. |
| Total Purchase Cost (via Purchase Invoice) | Purchase Invoices linked to the project. |
| Total Consumed Material Cost (via Stock Entry) | Stock Entries linked to the project. |
| Total Sales Amount (via Sales Order) | The linked Sales Order. |
| Total Billed Amount (via Sales Invoice) | Sales Invoices linked to the project. |
| Gross Margin and Gross Margin % | The billed amount minus the costs. |
Enter your own Estimated Cost to compare with these values. See How project costing works.
To collect progress updates from the project users by email, see Collect project progress by email.