View a Production Plan with the Plan Visualizer ​

Version 17

This feature is in ERPNext version 17, which is in development. ERPNext version 16 does not have it.

After you submit a Production Plan, its work spreads across Work Orders, subcontracting Purchase Orders, and Material Requests. To check whether you can start production, you would open each of them and check the stock of each raw material.

The Plan Visualizer puts this information on one screen. It shows:

  • How much of the plan is produced.
  • Whether the raw materials are available, or still need to be ordered.
  • Which Work Orders and Purchase Orders exist, and which are not created yet.
  • When each job is scheduled on the shop floor.

The Plan Visualizer is read-only. It does not change any data.

When to use it ​

Production planners, plant managers, and supervisors use it to follow a plan until it is complete. For example:

  • Is this plan on track?
  • What stops me from starting production?
  • Did someone forget to create a Work Order?
  • Which raw material is short?
  • What runs on which machine this week?

Open the Plan Visualizer ​

  1. Open a submitted Production Plan.
  2. Select View > Plan Visualizer.

You can also search for Production Plan Visualizer in the search bar and pick a Production Plan.

What the screen shows ​

  • Items to Manufacture: the finished goods and sub-assemblies with their planned, produced, and pending quantities.
  • Material Readiness and Raw Materials: the required, requested, ordered, and in-stock quantities of each raw material.
  • Work Orders and other documents: the orders linked to each row.
  • Schedule: a timeline by item or by workstation. The schedule shows only after you schedule the plan.