Production planning and forecasting reports ​

These reports help you plan what to make and forecast demand. Open each report from the search bar.

Production Planning Report ​

Shows, for open orders, whether the finished goods and raw materials are available. Use it in make-to-order production to decide which order to make first. Unavailable finished goods and raw materials show in red.

The report allocates the available stock to the orders in the order of Order By. When stock arrives, the report allocates it to the next order.

FilterWhat it does
Based OnThe orders to plan: Sales Order, Material Request, or Work Order.
Document NameOne order to plan.
Raw Material WarehouseWhere to check raw material stock.
Order ByDelivery Date or Total Amount.
Include Sub-assembly Raw MaterialsIncludes the raw materials of sub-assemblies.

For example, a furniture maker gets orders for tables and chairs. The stock is enough for only one of them. The report, ordered by Delivery Date, shows that the tables are due first. The planner starts the tables and orders raw materials for the chairs.

Production Plan Summary ​

Shows, for one Production Plan, each finished good and sub-assembly with its Work Order or Purchase Order, the ordered quantity, the produced or received quantity, and the pending quantity.

Filter: Production Plan.

Exponential Smoothing Forecasting ​

Forecasts demand from past Sales Orders, Delivery Notes, or Quotations with the exponential smoothing method.

How the forecast works ​

  1. The forecast of the first period is the average of all past periods.
  2. The forecast of each next period is the last forecast plus the forecast error multiplied by the smoothing constant. The forecast error is the actual demand minus the forecast.

The smoothing constant is a number between 0 and 1. The default 0.3 gives good results in most cases. A higher value follows recent demand more closely.

Exponential smoothing formula

Filters ​

FilterWhat it does
CompanyThe company to forecast for.
From Date, To DateThe forecast period. By default from today to one year ahead.
Based On DocumentSales Order (default), Delivery Note, or Quotation.
Based OnForecast the quantity or the amount.
Based On Data ( in years )How many years of past data to use.
PeriodicityMonthly, Quarterly, Half-Yearly, or Yearly.
Smoothing ConstantA value between 0 and 1.
Item Code, WarehouseNarrow the forecast.

To enter a forecast for MRP, use a Sales Forecast. See Plan material requirements with MRP.

Material Requirements Planning Report ​

Calculates the raw materials and components needed for a Master Production Schedule, and when to order them. See Plan material requirements with MRP.