Set BOM costing and currency
A BOM shows an estimated production cost in its Costing tab: Raw Material Cost, Operating Cost, Secondary Items Cost, and Total Cost. This page shows how to control the rates behind these costs.
Choose where component rates come from
In the More Info tab, set Rate Of Materials Based On:
| Option | Rate of each component |
|---|---|
| Valuation Rate | The current valuation rate of the item, from purchase receipts, manufacture entries, or stock reconciliations. An item with no stock transactions has no valuation rate. |
| Last Purchase Rate | The rate of the last purchase of the item. |
| Price List | The rate in the Price List that you select. Learn about Item Price. |
The operating cost comes from the hourly rate of each workstation and the operation time.
Cost a BOM in another currency
You can see the production cost in a currency other than the company currency. Set the currency before you submit the BOM.
- In the More Info tab, select the Currency. ERPNext fills in the Conversion Rate.
- In Rate Of Materials Based On, select an option:
- Price List: select a price list in that currency. ERPNext takes the rates in that currency.
- Valuation Rate or Last Purchase Rate: ERPNext converts the rates from the company currency.
For example, your company currency is INR and you import plastic from Japan. Create a buying price list "Import Japan" in JPY, select JPY as the BOM currency, and select Price List > "Import Japan".
The Costing tab shows the costs in the BOM currency and in the company currency.
Update the cost of a BOM
Component rates change over time. To refresh the costs of a submitted BOM, open it and select Update Cost.
To update all BOMs:
- Once: open the BOM Update Tool and select Update latest price in all BOMs.
- Every day: select Update BOM Cost Automatically in Manufacturing Settings.