Replace a BOM and update costs with the BOM Update Tool ​

The BOM Update Tool does two jobs:

  • It replaces a sub-assembly BOM with a new BOM in every parent BOM.
  • It updates the costs of all BOMs from the latest raw material rates.

To open it, search for BOM Update Tool in the search bar.

Replace a sub-assembly BOM ​

For example, a computer BOM uses a CPU sub-assembly. The CPU BOM has a 250 GB hard disk. You now use a 950 GB hard disk.

  1. Create and submit a new BOM for the CPU with the new hard disk.
  2. Open the BOM Update Tool.
  3. In Current BOM, select the old CPU BOM.
  4. In New BOM, select the new CPU BOM.
  5. Select Replace.

ERPNext replaces the old CPU BOM with the new one in the computer BOM and in every other parent BOM that uses it.

WARNING

The tool replaces only BOMs of sub-assemblies. It cannot replace a raw material that has no BOM of its own. To change a raw material in a parent BOM, cancel and amend the parent BOM, or create a new one.

Update the cost of all BOMs ​

Select Update latest price in all BOMs. ERPNext updates the cost of every BOM from the latest valuation rate, price list rate, or last purchase rate of the raw materials. The update runs as a background job and can take a few minutes.

To run this update every day, select Update BOM Cost Automatically in Manufacturing Settings.