BOM options reference
This page lists the BOM settings that change how ERPNext uses a BOM. To create a BOM, read Create a Bill of Materials.
BOM Configuration tab
| Setting | What it does |
|---|---|
| Is Active | Only active BOMs can be selected in Work Orders and Production Plans. Clear it to stop using a BOM. |
| Is Default | Work Orders and Production Plans use this BOM for the item by default. |
| Set rate of sub-assembly item based on BOM | Takes the rate of each sub-assembly from the cost of its BOM. If cleared, ERPNext uses the valuation rate of the sub-assembly. ERPNext ignores this setting for phantom items. |
| Is Phantom BOM | The BOM makes no stock item. It only groups raw materials. The item to manufacture must be a non-stock item. When this item is a component in another BOM, ERPNext always explodes it into its raw materials. |
| Allow Alternative Item | Lets you replace a component with an alternative item in Work Orders. Learn about Item Alternative. |
| Quality Inspection Required | Makes a quality inspection mandatory for this BOM. Select the Quality Inspection Template to use. |
| Default Source Warehouse | The warehouse from which components are taken by default. |
| Default Target Warehouse | The warehouse where the finished good goes by default. |
| Based On (Consume Components) | Overrides the backflush method of Manufacturing Settings for this BOM. See Create a Bill of Materials. |
Component row options
| Setting | What it does |
|---|---|
| Item operation | The operation that uses this component. |
| Source Warehouse | The warehouse where this component is stored. |
| Allow Alternative Item | Allows an alternative for this component. |
| Include Item In Manufacturing | Clear it for a cost row that ERPNext must not transfer or consume. |
| Do Not Explode | Keeps the sub-assembly as one item in the exploded list, instead of its raw materials. ERPNext clears and locks this checkbox for phantom items. |
| Sourced by Supplier | In a subcontracting BOM, marks a material that the supplier buys. See Set up subcontracting. |
When to use Do Not Explode
A company makes laptops to order. A laptop needs a motherboard and a keyboard. Both are sub-assemblies. Motherboards take long to make, so the company makes them in advance and keeps them in stock.
In the laptop BOM, select Do Not Explode on the motherboard row and leave it cleared on the keyboard row. The laptop Work Order then uses motherboards from stock, and plans the raw materials of the keyboard.
Cost Allocation and Process Loss
| Setting | What it does |
|---|---|
| % Cost Allocation | The share of the raw material cost that goes to the main finished good. The rest goes to the secondary items. |
| % Process Loss | The share of the output quantity that production loses. ERPNext calculates the Process Loss Qty. |
More Info tab
| Setting | What it does |
|---|---|
| Rate Of Materials Based On | Where component rates come from. See Set BOM costing and currency. |
| Project | Links the BOM to a Project, for example in engineer-to-order production. |
Website tab
Select Show in Website to publish the BOM on your website, for example for open-source hardware. Show Items and Show Operations add the components and the operations to the page.