Track semi-finished goods by operation ​

A semi-finished good is the output of one operation that becomes the input of the next operation. For example, a bicycle factory makes a chain in one operation and uses it in assembly.

With Track Semi Finished Goods, each operation of a BOM has its own output and its own materials. When you complete the Job Card of an operation, ERPNext consumes its raw materials and adds its semi-finished good to stock. The last operation produces the finished good and consumes the semi-finished goods.

INFO

This feature is new in ERPNext v16.

Prerequisites ​

  • An item for each semi-finished good.
  • Optional: a BOM for each semi-finished good. You can instead add its raw materials in the operation.

Set up the BOM ​

  1. In the BOM, select With Operations and Track Semi Finished Goods.
  2. In each row of the Operations table, set:
    • The Operation, the Operation Time, and the Workstation or Workstation Type.
    • FG / Semi FG Item: the output of the operation, and Qty to Produce.
    • BOM No of the output, or select Add Raw Materials to add the materials of this operation.
    • The warehouses: Source Warehouse, WIP Warehouse, and Finished Goods Warehouse.
    • Is Final Finished Good on the last operation.
  3. Optional: select Skip Material Transfer to consume materials without a transfer to the Work-in-Progress Warehouse. Then select Backflush Materials From WIP Warehouse to consume them from the Work-in-Progress Warehouse instead of the source warehouse.
  4. Optional: select Is Subcontracted for an operation that a supplier performs. You can then create a subcontracting Purchase Order from its Job Card with Make Subcontracting PO.
  5. Submit the BOM.

Run production ​

  1. Create and submit a Work Order for the finished good. ERPNext creates one Job Card for each operation. The Work Order shows the output and the materials of each operation.
  2. For each Job Card, in order:
    1. If the operation does not skip the transfer, transfer its raw materials to the Work-in-Progress Warehouse.
    2. Select Start Job, and Complete Job when the work is done.
    3. Select Make Stock Entry to create the Manufacture Stock Entry for the semi-finished or finished good. ERPNext asks whether to submit it. If you answer no, it stays a draft.

Where ERPNext consumes the raw materials from depends on the operation settings:

Skip Material TransferBackflush Materials From WIP WarehouseConsumes from
ClearedNot shownWork-in-Progress Warehouse, after you transfer
SelectedSelectedWork-in-Progress Warehouse, without a transfer
SelectedClearedSource Warehouse

When all Job Cards are complete, ERPNext completes the Work Order.

Workstation dashboard ​

Each workstation has a dashboard with its Job Cards. From the dashboard you can:

  • Transfer raw materials from the source warehouse to the Work-in-Progress Warehouse.
  • Start a job. ERPNext fills in the employee of the logged-in user.
  • Pause, resume, and complete a job. When you complete a job, ERPNext asks for the quantity and creates the Manufacture Stock Entry.

Subcontracted operations do not show on the workstation dashboard.

Workstation dashboard with Job Cards