Plan production with a Production Plan
A Production Plan collects the demand for finished goods from many Sales Orders or Material Requests. From the plan, you create the Work Orders for the finished goods and sub-assemblies, and the Material Requests for the raw materials.
Prerequisites
- A submitted, default BOM for each item to make. The plan fetches only items that have a BOM.
- Submitted Sales Orders or Material Requests, unless you add items by hand.
Get the items to make
- Open the Production Plan list and select New.
- In Get Items From, select Sales Order or Material Request. To add items by hand, leave it empty and go to step 6.
- In Filters, narrow the documents, for example by Customer, Item Code, or date range.
- Select Get Sales Orders or Get Material Request. ERPNext fills in the orders.
- Select Get Finished Goods. ERPNext fills in the Assembly Items table with the items that have a BOM.
- Review each row in Assembly Items: the BOM No, the Planned Qty, the Finished Goods Warehouse, and the Planned Start Date.
To combine rows of the same item with the same BOM into one row, select Consolidate Sales Order Items before you get the finished goods.
To include the raw materials of the sub-assemblies in a row, open the row and select Include Exploded Items.
Add sub-assemblies
- In the Sub Assembly Items section, optional: select a Sub Assembly Warehouse.
- Select Get Sub Assembly Items. ERPNext fills in the sub-assemblies from the BOMs of the finished goods.
- In each row, select the Manufacturing Type:
- In House: you make it. ERPNext creates a Work Order.
- Subcontract: a supplier makes it. Select the Supplier. ERPNext creates a subcontracting Purchase Order.
- Material Request: you buy it. Select Get Items for Purchase Only to add it to the raw materials table.
To combine sub-assemblies with the same item, warehouse, BOM, and manufacturing type into one row, select Consolidate Sub Assembly Items. You can then make one Work Order for several finished goods.
Order only what you need
Select Consider Projected Qty in Calculation to subtract the projected quantity of each sub-assembly from the quantity to order. The projected quantity includes stock and open Work Orders. ERPNext checks the Sub Assembly Warehouse and its child warehouses.
For example, you plan 100 units of item A. Each A needs one sub-assembly B. B has 20 units in stock and 20 units in an open Work Order. ERPNext sets Qty to Order to 100 − 40 = 60. Learn about projected quantity.
Plan raw materials
Fill in the Raw Materials table before you submit, then create Material Requests after you submit. See Plan raw materials for production.
Create Work Orders and Material Requests
- Submit the Production Plan.
- Select Create > Work Order / Subcontract PO. ERPNext creates Work Orders for the items to make in house, and subcontracting Purchase Orders for the subcontracted items.
- Select Create > Material Request to request the raw materials.
The Status of the plan changes as the work progresses: Not Started, In Process, Material Requested, and Completed.
Close a Production Plan
Close a plan that you will not finish, for example when you made an item outside the plan or when plans changed. ERPNext then creates no more Work Orders or Material Requests from it.
- Open the submitted Production Plan.
- Select Status > Close.
To use the plan again, select Status > Re-open.