Manufacture for a customer with Subcontracting Inward
In Subcontracting Inward, a customer sends you raw materials and you make finished goods for them. It is the reverse of subcontracting to a supplier.
INFO
The Subcontracting Inward Order is new in ERPNext v16.
With Subcontracting Inward you can:
- Receive and track the customer's raw materials without an effect on your books.
- Use extra materials from the customer, and add your own materials and bill them.
- Reserve the customer's materials so that no other order uses them.
- Create more Work Orders after a process loss.
- Return raw materials to the customer, and take back finished goods from the customer.
- Deliver overproduced quantities and secondary items, if you allow it.
- Deliver the same serial numbers and batches that you produced for the order.
Prerequisites
- A warehouse for each customer. Create a warehouse and select the customer in its Customer field. We recommend a group warehouse that holds all customer warehouses.
- The customer's raw materials. On each item, select Is Customer Provided Item. These items cannot be purchased, so Allow Purchase must be cleared.
- A service item to bill the customer. Clear Maintain Stock on it.
- The finished good. Select Is Subcontracted Item on it.
- A BOM for the finished good with at least one customer-provided item.
- A Subcontracting BOM that links the service item to the finished good. It is optional if the finished good has a default BOM. See Set up subcontracting.
Step 1: Create a subcontracted Sales Order
- Create a Sales Order and select Is Subcontracted. The item table changes.
- In Item Code, select the service item. ERPNext fills in the finished good from the Subcontracting BOM. If several finished goods match, ERPNext asks you to choose one.
- Enter the quantity of the service item. ERPNext calculates the finished good quantity from the conversion factor.
- Submit the Sales Order.
Step 2: Create a Subcontracting Inward Order
- In the Sales Order, select Create > Subcontracting Inward Order.
- Select the Customer Warehouse. If the customer has only one warehouse, ERPNext fills it in.
- Select the Delivery Warehouse for each finished good, or use Set Delivery Warehouse for all rows.
- Optional: open a finished good row and select Include Exploded Items to list the raw materials of the sub-assemblies.
- Optional: lower the finished good quantity to split the Sales Order into several Subcontracting Inward Orders.
- Submit the Subcontracting Inward Order.
Step 3: Receive the raw materials
- In the Subcontracting Inward Order, select Receive > Material from Customer. ERPNext creates a Stock Entry with the required raw materials.
- Optional: add extra customer-provided items. For each extra item, select the finished good in Against Finished Good.
- Optional: enter a basic rate for each item, for tax purposes. The rate has no effect on your stock value. The accounting ledger of the entry shows zero.
- Submit the Stock Entry.
You can receive more materials at any time, even after you receive the full quantity of the BOM.
Step 4: Make the finished goods
- Reload the Subcontracting Inward Order and select Create > Work Order. ERPNext creates a Work Order for each finished good, for the quantity that the received materials allow.
- Run the Work Orders as usual.
Extra raw materials used in the Manufacture Stock Entries are added to the Required Items table of the Subcontracting Inward Order.
Step 5: Deliver the finished goods
- Reload the Subcontracting Inward Order and select Create > Subcontracting Delivery.
- Check the Stock Entry and submit it.
By default ERPNext delivers only the agreed quantity and no secondary items. To change this, in Selling Settings, in the Subcontracting Inward tab:
- Select Allow delivery of overproduced quantity to deliver more than the agreed quantity.
- Select Deliver secondary Items to deliver the secondary items too.
Step 6: Bill the customer
From the Sales Order, create a Delivery Note for the service item, then a Sales Invoice. The invoice includes the raw materials that you supplied yourself.
You can deliver and bill the service item even without a Subcontracting Inward Order.
Returns
From the Return menu of the Subcontracting Inward Order:
- Raw Materials to Customer: return raw materials, for example after a quality failure or a wrong delivery.
- Finished Goods Return: take back finished goods that you delivered.
Limits and good practice
- ERPNext creates stock reservation entries for this flow even when stock reservation is disabled in Stock Settings. Do not cancel them.
- Unused raw materials of one Subcontracting Inward Order cannot go to another order. Return them to the customer and receive them again against the other order. No physical movement is needed.
- When an item has several batches, use a serial and batch bundle. Do not add the same item in several rows.
- Work Orders created from a Subcontracting Inward Order do not support alternative items.
- Continuous material consumption and Disassembly Orders are not supported. Inventory dimensions are not officially supported.
- Use a batch item with Batch-wise Valuation for the finished good. Otherwise FIFO can value the delivery with older purchased stock of the same item.