Create and manage tasks
A Task is one piece of work that someone must finish, for example Design the prototype. Tasks usually belong to a project. Their progress makes up the project's progress, and the time logged against them makes up its cost.
Create a task
- Open the Task list and select Add Task.
- Enter the Subject.
- Select the Project.
- Save.
To create a task from a project, open the project's Connections tab and select + next to Task. ERPNext fills in the project.
Plan the task
| Field | What it does |
|---|---|
| Status | Open, Working, Pending Review, Overdue, Completed, or Cancelled. ERPNext sets Overdue every day for open tasks past their Expected End Date. |
| Priority | Low, Medium, High, or Urgent. |
| Expected Start Date and Expected End Date | The planned dates. |
| Expected Time (in hours) | The planned effort. |
| % Progress | How much of the task is done. Used by the Task Progress and Task Weight methods of the project. |
| Weight | The share of the task in the project, for the Task Weight method. |
| Is Milestone | Marks the task as a milestone of the project. |
| Type | A Task Type, for example User Training, to filter tasks. |
| Color | The color of the task in the Gantt view. |
| Issue | The support Issue that the task comes from. |
| Task Description | What to do. |
In the More Info tab, set the Department and the Company that does the task. The company can differ from the project's company, for example when a sister company does part of the work.
Break a task into subtasks
- Create the parent task and select Is Group.
- In each subtask, select the parent in Parent Task.
Add dependencies
When a task cannot finish before another task, add the other task in the Dependent Tasks table on the Dependencies tab. The Gantt view shows the dependencies as arrows. See View tasks as a Gantt chart, Kanban board, or calendar.
Follow time and cost
When people log time against the task in timesheets, ERPNext fills in:
- Actual Start Date (via Timesheet) and Actual End Date (via Timesheet).
- Actual Time in Hours (via Timesheet).
- Total Costing Amount (via Timesheet) and Total Billable Amount (via Timesheet).
Complete a task
Set Status to Completed. ERPNext shows Completed On and Completed By. The Delayed Tasks Summary uses Completed On to calculate the delay.
To change the status of many tasks at once, select them in the Task list and select Set as Open or Set as Completed in the menu.
Template tasks
A task with Is Template selected is part of a project template. It uses Begin On (Days) and Duration (Days) instead of dates.