Project reports ​

The project reports show progress, time, billing, material, and delays. To open a report, search for its name in the search bar.

Project Summary ​

Shows each project with its status, start and end dates, and the number of linked tasks and timesheets. Use it to see the state of all projects at a glance.

Daily Timesheet Summary ​

Lists the timesheet rows of a period, with the activity, the hours, the task, and the project. Use it to review how people spent their time each day.

Timesheet Billing Summary ​

Shows the working hours, billable hours, billing rates, and billing amounts of timesheets in a period. Use it to review time-and-material billing.

Project Wise Stock Tracking ​

Shows the Items purchased and issued for each project, with the project status, the project value, and the start and completion dates. Use it to follow material use against each project.

Delayed Tasks Summary ​

Lists tasks with their progress and their expected start and end dates, and shows which are on track and which are delayed. The chart counts the On Track and the Delayed tasks for your filters.

ERPNext calculates the delay of each task as follows:

TaskDelay
Completed, with Completed On setCompleted On − Expected End Date
Not completed, or Completed On not setToday − Expected End Date

Completed On shows on the task when its status is Completed.

Delayed Tasks Summary report with a chart of on-track and delayed tasks