Reuse task plans with project templates
A Project Template is a list of tasks that you repeat in similar projects, for example the steps of an installation job. When you create a project from the template, ERPNext creates the tasks and calculates their dates.
Prerequisites
- The template tasks exist. A template task is a Task with Is Template selected. Its status is Template.
Create template tasks
- Open the Task list and select Add Task.
- Enter the Subject.
- Select Is Template.
- Set Begin On (Days): the number of days after the project start when the task begins.
- Set Duration (Days): how many days the task takes.
- Save. Repeat for each task in the plan.
Create the project template
- Open the Project Template list and select Add Project Template.
- Enter the name of the template.
- Optionally, select the Project Type.
- In the Tasks table, add the template tasks in order.
- Save.
Use the template
- Create a project.
- Select the template in From Template.
- Set the Expected Start Date.
- Save the project.
ERPNext creates a task for each template task. It calculates each task's Expected Start Date and Expected End Date from Begin On (Days) and Duration (Days), and skips the holidays in the company's holiday list.
To stop using a template, select Disabled on it.