Run your first project ​

In this tutorial, you run one customer job as a project, from the order to completion. At the end, you have a completed project with its tasks, its purchases, and its recorded time.

What you will build ​

A company receives an order for a custom metal storage rack. You will:

  1. Record the order as a Sales Order.
  2. Create a project from the order.
  3. Break the work into tasks.
  4. Buy the raw material for the project.
  5. Record the time spent on the work.
  6. Complete the tasks and the project.

Before you start ​

  • A Customer for the order.
  • An Item named Storage Rack that you sell.
  • The raw material Items, for example Steel Section and Paint, and a supplier for them.
  • An Employee who records time.
  • An activity type, for example Execution.

Step 1: Create the Sales Order ​

  1. Open the Sales Order list and select Add Sales Order.
  2. Select the customer and add the Storage Rack Item with its quantity and rate.
  3. Submit the Sales Order.

Step 2: Create the project from the order ​

  1. In the submitted Sales Order, select Create > Project.
  2. Check the Project Name and save the project.

The project is linked to the customer and the Sales Order. Its Total Sales Amount (via Sales Order) shows the order value.

Step 3: Add the tasks ​

  1. In the project, open the Connections tab and select + next to Task.
  2. Create a task named Cutting and welding, with an Expected Start Date and an Expected End Date.
  3. Repeat for Painting and Final assembly.

You now have a project with three open tasks.

Step 4: Buy the raw material ​

  1. Create a Purchase Order for the steel and the paint.
  2. In each Items row, set the Project to your project.
  3. Submit the Purchase Order. When the bill arrives, create the Purchase Invoice from it.

When the Purchase Invoice is submitted, its cost shows in the project's Total Purchase Cost (via Purchase Invoice).

Step 5: Record the time ​

  1. Create a Timesheet for the employee.
  2. In the Time Sheets table, add a row with the activity type, the hours, the project, and the Cutting and welding task.
  3. Submit the timesheet.

The task's Actual Time in Hours (via Timesheet) and Total Costing Amount (via Timesheet) now include the hours. The project's Total Costing Amount (via Timesheet) updates too.

Step 6: Complete the work ​

  1. As each task finishes, open it and set Status to Completed.
  2. After the last task, open the project.

With the default % Complete Method of Task Completion, % Completed reaches 100 and the project's status changes to Completed.

You now have a completed project with its sales amount, its purchase cost, and its time cost.

Next steps ​