Capitalize an asset from parts and services
Some assets are built, not bought whole. For example, you build a test machine from purchased parts, an old conveyor, and an installation service. Capitalization moves the cost of these inputs into one fixed asset, instead of booking them as expenses.
In ERPNext, the asset that you build is a composite asset. An Asset Capitalization collects the inputs and adds their value to it.
Prerequisites
- A fixed asset Item and an asset category for the asset that you build.
- The stock Items, the assets, and the service Items that you will use.
- The stock Items are in a warehouse.
Step 1: Create the composite asset
- Create an asset with the fixed asset Item.
- Set Asset Type to Composite Asset.
- Save it. Do not submit it. Its status is Work In Progress.
ERPNext shows Capitalize this asset before submitting.
Step 2: Add the inputs
- On the draft asset, select Capitalize Asset. ERPNext opens an Asset Capitalization with the Target Asset set. You can also open the Asset Capitalization list and select the target asset.
- Select the Company and check the Posting Date.
- If you keep several sets of books, select the Finance Book.
- Add the inputs:
- Stock Items: parts that you take out of a warehouse.
- Assets: existing assets that become part of the new asset.
- Services: service Items, such as installation, with an expense account and an amount.
- Check Total Value. ERPNext calculates it from the inputs.
You need at least one input. Open a row with the edit icon to set its warehouse, quantity, rate, account, or cost center.
Step 3: Submit and finish the asset
- Submit the Asset Capitalization. ERPNext:
- Takes the stock Items out of their warehouses.
- Depreciates each consumed asset up to the posting date and removes it from the books. Its status changes to Capitalized.
- Books the service amounts.
- Adds the total value to the Net Purchase Amount of the target asset.
- Open the target asset, set its depreciation details, and submit it.
Troubleshooting
Target Asset needs to be composite asset. Set Asset Type to Composite Asset on the target asset.
Target Asset cannot be submitted. The target asset must be a draft. Capitalize first, then submit the asset.
ERPNext asks for at least one input. Add a row to Stock Items, Assets, or Services.
A service row does not save. Fill in the Item, the expense account, the quantity, the rate, and the cost center.